For sale Industrial land 250 MW potential RTE study approved

22-hectare industrial land – 250 MW data center potential

Industrial zone, central France

Reference: VT-2025-001 Pre-approved by local authorities Posted on

Price

€18M

Land

+ RTE grid connection: €13M

Land area
22 ha
Total power
250 MW
Substation distance
< 5 km
Power delivery lead time
60 months

At a glance

  • ✓

    Exploratory RTE study

    Approved

  • ✓

    PTF

    Approved

  • ✓

    Local pre-approval

    Authorities on board

  • 60

    Months to delivery

    After PTF

Request the full file

A strategic opportunity

220,460 m² (22-hectare) plot in an industrial zone in central France. The site offers rare potential for a 250 MW data center, including high-density AI workloads.

Key benefits

  • Industrial zone pre-approved by local authorities
  • Exploratory RTE study approved for 250 MW
  • RTE substation less than 5 km away
  • 2 hours from Lyon by car
  • Undeveloped plot, ready for development
  • Suited to a high-density AI data center

Grid connection

The exploratory RTE study has been approved for 250 MW. The substation is less than 5 km away; the connection cost is estimated at €13M, with power delivered within 60 months of the PTF (RTE's connection offer). No further power extension is planned.

Location

In the centre of the country, the site can serve the whole of France. Lyon is a 2-hour drive away, which keeps logistics and site operations simple.

Next steps

The building permit and the ICPE environmental application have not been filed yet.

Site details

Land

Land area
22 ha
Site type
Greenfield
Zoning
Industrial zone

Power infrastructure

Total power
250 MW
Grid operator
RTE
Substation distance
< 5 km
Estimated connection cost
€13M
Power delivery lead time
60 months
Power supply
Grid

Permits and approvals

Local pre-approval
Approved
RTE study
Exploratory study approved
PTF (RTE connection offer)
Approved
Building permit
Not filed
ICPE (environmental permit)
Not filed

Access

Lyon
2 h